Appendix B – Complete Detailed Building Schedule
This appendix [excerpt] contains [part of the total] compiled detailed building schedule -a list from the fifteen partial lists (A-O) presented in the chapters of this book. The tasks shown should adequately cover the majority of details needed to complete a dwelling in chronological order.Verify some municipal requirements with your city, county, and state authorities, as those detailed in this book reflect mostly Tennessee, Colorado, and Florida stipulations. Regulations, dimensions, and quantities are based on state codes, local requirements, and the Uniform Building Code that change frequently.
Planning & Preliminary - Part A [1 part of 15 parts of the total schedule]
The below partial list, Part A  of the Detailed Building
Schedule, is from Chapter 2:
- Record
 Data: area (sq. ft.): 1st floor ________ 2nd
 floor ________ =Conditioned area (inside brick.) Garage area
 (outside blocks)= ________.   Miles to Job______      Slab
 area(block to block, w/garage)_____.  Lin. Ft. of outside footers 
 _____1st floor ____2nd floor.  _______Lineal
 ft. of perimeter with garage. 
 
 
- Preliminary
 Preparation:  Rough estimate of Lot cost. Get wetlands study
 (Florida) on lot,  _________________ environmental engineer
 ________________phone.
 
- Lot
 Purchase Date ______________, Closing title Co.
 _____________________phone. Quit Claim Deed to LLC before
 construction permit pulled.
 
- Get
 developer’s SWPPP32
 (storm water pollution prevention plan) permit number before closing
 lot purchase. –See Chapter 4.
 
- Liability
 insurance coverage may be increased by an umbrella policy if lot
 owned personally (not by LLC). 
 
 
- Record
 Deed with county-Money order, Return envelope, certified (TN,)
 Verify recorded).
 
- Get
 address assignment for lot before Bldg. Permit & closing for lot
 description. _________________  Bldg. Dept. phone number.
 
- LLC
 Needs Contractor’s Liability Insurance (cheaper through Home
 Builder's Assn.) 
 
 
- Need
 Workman’s Compensation insurance to cover Subs.
 
- Need
 Builder’s Risk Insurance.
 
- 
 Warranty company: (HBW5 or BBHWA6)
 “Notice of Starts” or “Construction Indication” form before
 breaking ground. BBHWA call for “Risk Management number”
 _______________ phone number.
 
-----------------------------------------------------------------------------------------------------
        
Drawings & Estimates - Part B [1 part of 15 parts of the total schedule]
The below partial list, Part B, is from Chapter
3:
- Detailed
 estimate of construction costs (Appendix F.)
 
- Drawing
 pages required  by code enforcement for permit application:
 (e.g., per Shelby County, TN,  3 site, 5 floor, 2 roof, 2 joist,
 1 elec, 1 plumbing, 1 slab section, stair detail, cornice detail,
 sections & other details.) (For the state of FL see  List in the
 Bldg. Code.) Include 2 Duplicate plan sets for use in builder's
 office. 
 
 
- Additional
 Plan Sets needed for early QUOTES from subs & suppliers: 
 
 
- Electrical,
  
 
- HVAC, 
 
 
- Plumber, 
 
 
- Framer,
 trusses, 
 
 
- lumber.
 Request return of plans with proposals.
 
- Small
 scale (1/8” = 1’) for convenience and copying.
 
- Have
 FL Engineer stamp and produce structural drawings and details.
 
- Truss
 company quote (truss drawing details come with truss order) -
 Chap.8.
 
- Architectural
 Control Committee review in your subdivision / HOA.
 
- Accurate
 quotes desired early (after lot purchase, design, & prior to
 grading) are:
 
- Grading &
 lot clearing quote
 
- Roof
 Trusses and Truss joists
 
- Appliances
 (to lock in price): Microwave, oven, Double or separate 2nd
 oven & Range /downdraft, trash compactor, dishwasher, disposer,
 sink
 
- Framing
 quote
 
- Stone
 countertops (cultured? quartz composite?)
 
- Wrought
 Iron: Gate, crawl space grilles, mailbox, balcony, stair rails
 
- HVAC
 
- Plumbing
 (see Chapter 7 for discussion)
 
- Electrical
 (see Chapter 10 for discussion)
 
- Slab labor
 quote
 
- Window &
 exterior Door quote.
 
[continued in book, Total schedule is 15 parts - 2 shown on this post]